
*Please note that the links to the content in this Part will direct you to Westlaw AU.
To purchase an article, please email: LTA.Service@thomsonreuters.com or contact us on 1300 304 195 (Australian customers) or +61 2 8587 7980 (international customers) during business hours (Mon-Fri, 8am-6pm AST).
The latest issue of the Building and Construction Law Journal (Volume 34 Part 1) contains the following material:
- Is the Traditional Contract Superintendent Model Outmoded? – Michael Christie SC
Articles
A Contractual Path Around Proportionate Liability? – Grant Lubofsky
Proportionate liability regimes have been operational in various forms for almost 20 years and the scope and effect of those regimes have, after considerable judicial attention, been largely settled. Nevertheless, there remains one crucial question still to be determined by the Courts which continues to plague litigants: can a claim for damages made purely under contract (eg, under an indemnity) “arise from a failure to take reasonable care” thereby constituting an “apportionable claim”? This article analyses the judicial consideration of this question to date, in addition to weighing the merits of the contrasting approaches in light of the words and purpose of the statutes. This article concludes that the better view is that a claim made solely under contract cannot constitute an apportionable claim for the purposes of the proportionate liability regime, and that a plaintiff is entitled to pursue a sole defendant for damages under such an action.
Project Testing and Commissioning is often the singularly critical event signalling the transitional phase from construction risk to operational risk. The factual and legal complexities around project completion and project handover on a site before, during and after testing and commissioning can often serve to confuse whether a project has, at law and under contract, in fact transitioned to operational status. The distinction though is an essential one, not just for risk financers, but for Principals who do not wish to bear the costs and delays of defects in workmanship, materials and processes of a Contractor, and for Contractors who do not wish to bear responsibility for operational concerns for plant effectively delivered. The testing and commissioning phase can represent a period of blurred lines as is demonstrated in the following article.
REPORTS
- Aalborg CSP A/S v Ottoway Engineering Pty Ltd
- Abergeldie Contractors Pty Ltd v Fairfield City Council
- Fitz Jersey Pty Ltd v Atlas Construction Group Pty Ltd
For the PDF version of the table of contents, click here: BCL Vol 34 No 1 Contents.
Click here to access this Part on Westlaw AU
For general queries, please contact: tlranz.journal.orders@thomsonreuters.com.